New Generator At Queen’s Park Power Plant Going Into Service 

Having successfully started the new engine for the first time, the Grenlec team  is preparing to put the engine into full service over the next week.

During the installation period over the past 11 weeks, special civil, mechanical and electrical  works have been completed in preparation for the commissioning of the new generator, which  will increase the Company’s overall power generation capacity to 52MW.

Clive Hosten, Grenlec’s Chief Engineer, notes, “We are fortunate to have had a competent  installation team and we look forward to the engine going into full service”.

Over the next three weeks, there is the possibility of unplanned service interruptions as the team  integrates the new engine into its operating system.

“We want customers to be aware that while Grenlec is making every effort to avoid  inconvenience, it is not unusual for some disruptions to customers’ service, during the  commissioning, as the team resolves unforeseen challenges that may arise. Mr. Hosten added,  “Having prepared customers for the possibility of outages, we hope the preparatory work our  team has done will facilitate a smooth integration with little to no service interruptions”.

The Company anticipates that the new engine will be commissioned before the end of  September.

Grenlec apologises for any inconvenience that may arise and assures customers of its continued  commitment to reliably serving Grenada, Carriacou and Petite Martinique.

About adminrfm 3063 Articles
We, at Real fm are dedicated to change the recreation activities in the island Grenada. Our vision is to become widely known and respected as one of the best places to relax and have fun anywhere.